Project Management 4.0 - 5.0 (part A) Question Preview (ID: 53993)


Project Management 4.0 - 5.0. TEACHERS: click here for quick copy question ID numbers.

Adam's Construction has accepted a contract to build a six-story office building. The company is using a timeline from a two-story building project the company completed in the previous month to develop the schedule for this project. Adam's Construct
a) analogous estimating.
b) parametric estimating.
c) three-point estimating.
d) reserve analysis.

Which best describes the critical path slack?
a) the activities on the critical path
b) the delay after the drywall is completed in a house to allow it to dry
c) the earliest a new HVAC system can be ordered from a manufacturer
d) the earliest a new HVAC system can be ordered from a manufacturer without delaying the project

The project manager is creating an estimate to set up an office building's electrical system. He has twenty-two years of experience managing similar projects. The client needs the estimate quickly. Which type of estimate is he most likely to provide?
a) analogous estimating
b) parametric estimating
c) reserve analysis
d) three-point estimating

Chandler is setting up a time schedule for beta testing a new software project. Currently, the company has one computer lab compatible with his new program, and there are three other software programs being tested on that lab's systems. Chandler modi
a) critical path method
b) critical chain method
c) reserve analysis
d) schedule compression

Maria determines the project duration by overestimating what she calculates by 15%. Maria is using:
a) analogous estimating.
b) parametric estimating.
c) reserve analysis estimating.
d) three-point estimating.

Ashlyn's pottery project for art class must dry before she can put on a final coat of glaze. This is an example of a/an:
a) abstract dependency.
b) discretionary dependency.
c) external dependency.
d) mandatory dependency.

Craig would like to view a graphical representation of his project's work packages in a timeline bar chart format. Craig should create a:
a) Gantt chart.
b) milestone chart.
c) project schedule diagram.
d) schedule compression.

The project manager recognizes his team may fail to meet a deadline, so he assigns the team to do two activities in parallel. This is an example of schedule:
a) crashing.
b) fast tracking.
c) leading.
d) shortening.

Which process puts more resources on the critical path?
a) crashing
b) fast tracking
c) leading
d) shortening

Gwen is leading a Web design project and has determined that the optimistic time for completion is 2 months, the pessimistic time is 12 months, and the likely time for completion is 5 months. Using three-point analysis (TE = (O + 4L + P) รท 6), what i
a) 2.79 months
b) 3.29 months
c) 5 months
d) 5.67 months

Dennis is unable to estimate the duration of his project with certainty, so he decides to break down the work into activities. He then adds up the total quantity for each of the activity durations. Dennis is using:
a) analogous estimating
b) bottom-up estimating.
c) reserve analysis.
d) three-point estimating.

Eva has been hired to landscape the new community park. She has sixteen weeks to complete the project, which will take a total of twelve weeks. Eva decides to begin the project immediately so that she has extra time for weather delays. Eva is using:
a) analogous estimating
b) parametric estimating.
c) reserve analysis.
d) three-point estimating.

Andy prefers to set up furniture before hanging window treatments for his interior design projects. This is an example of a/an:
a) abstract dependency
b) discretionary dependency.
c) external dependency.
d) mandatory dependency.

Alex orders all of the plumbing supplies for his construction projects from the same vendor. Due to a recent fire, the vendor is unable to deliver the supplies when needed. This is an example of a/an:
a) mandatory dependency.
b) discretionary dependency.
c) external dependency.
d) abstract dependency.

Craig needs to weld the car chassis together before Jim can install the engine. This represents a/an:
a) abstract dependency.
b) discretionary dependency.
c) external dependency.
d) mandatory dependency.