The organizational structure where the project manager has the least amount of authority is a:
a) composite organization
b) functional organization
c) matrix organization
d) projectized organization

Andrew is the prom committee chairman. He is at the prom and realizes that the meal delivered to the attendees was steak and not chicken. Andrew makes the catering manager aware immediately that the chicken meal was agreed upon, so the steak meal is
a) planning
b) executing
c) monitoring
d) closing

Andrew is the prom committee chairman. He is on-site at the prom to make sure all vendors show up at the event and all vendors' activities are falling within the scope of work contracted. Which process stage is Andrew in?
a) initiating
b) executing
c) monitoring
d) closing

Joe holds a team meeting to discuss lessons learned. He is in which process stage?
a) planning
b) executing
c) monitoring
d) closing

Sierra is visiting and calling venues to see who is available to host her parents' anniversary party. What process stage is she in?
a) initiating
b) executing
c) monitoring
d) closing

Sierra is working with her sisters to determine how much money they have spent on their parents' anniversary party to calculate the funds remaining in their budget. What process stage is she in?
a) initiating
b) executing
c) monitoring
d) closing

Paul is contacting a list of potential suppliers to request price quotes for a key project material. He is in which process stage?
a) planning
b) executing
c) monitoring
d) closing

After a wedding, Christina meets with the newlyweds to deliver the photographs she took and get the customer's signature and payment for the work done. Which process stage is Christina in?
a) planning
b) executing
c) monitoring
d) closing

Alison holds weekly project team meetings to determine whether she needs to crash any project activities to help keep the project on track. What process stage is she in?
a) planning
b) executing
c) monitoring
d) closing

Tara is meeting with her stakeholders to determine the scope of work. What process stage is she in?
a) initiating
b) executing
c) monitoring
d) closing