Project I: Project Management Overview Question Preview (ID: 23489)


Project Management Overview. TEACHERS: click here for quick copy question ID numbers.

Activities performed to define a new project or a new phase of an existing project
a) Initiating
b) Monitoring and Controlling
c) Closing
d) Planning

Activities performed in order to establish the total scope of the project, define and refine the objectives, and develop the course of action that will be followed to achieve the objectives.
a) Initiating
b) Monitoring and Controlling
c) Closing
d) Planning

Activities performed to carry out and complete the work as defined in the project management plan.
a) Executing
b) Planning
c) Initiating
d) Closing

Activities performed to track, review, and regulate the execution of the project.
a) Monitoring and Controlling
b) Closing
c) Planning
d) Executing

Activities performed to finalize the project – to bring it to a conclusion and to meet contractual obligations.
a) Closing
b) Monitoring and controlling
c) Initiating
d) Planning

Defines the boundaries of the project and what is outside those boundaries.
a) Scope
b) Time
c) Cost
d) Quality

Establishing a timeline for completion of the project, including deadlines, benchmarks, and milestones.
a) Scope
b) Time
c) Cost
d) Quality

The amount of money that will be required to complete the project successfully.
a) Scope
b) Time
c) Cost
d) Quality

The ability of a process or product to satisfy both stated and implied needs, with those needs being defined by the stakeholders.
a) Scope
b) Time
c) Cost
d) Quality

he knowledge, skills, values, and attitudes of those working on the project.
a) Human Resources
b) Communication
c) Risk
d) Procurement

Two-way process of reaching mutual understanding in which participants not only exchange information, but also create and share meaning.
a) Human Resources
b) Communication
c) Risk
d) Procurement

A threat of a damage, liability, loss, or other negative occurrence that is caused by external or internal vulnerabilities, and that may be minimized or neutralized through preemptive action.
a) Human Resources
b) Communication
c) Risk
d) Procurement

The way that businesses and organizations purchase or obtain goods or services.
a) Human Resources
b) Communication
c) Risk
d) Procurement