Review Game Zone
Games
Test
Preview
Back
Match it!
Match it! Select the correct answer from the pull down...Good luck!
Which metric should Carol use to determine her project's future cost efficiency?
discretionary dependency
forecasting.
fast tracking
1500
to-complete performance index
1250
earned value management
schedule performance index
Alex prefers to complete the plumbing work in his construction projects before completing electrical work. This is an example of a/an:
discretionary dependency
forecasting.
fast tracking
1500
to-complete performance index
1250
earned value management
schedule performance index
In order to complete the finished attic remodel project on time, Brian decides to hang the ceiling fan while Petrina paints the walls. This is an example of schedule:
discretionary dependency
forecasting.
fast tracking
1500
to-complete performance index
1250
earned value management
schedule performance index
Tucker is the construction project manager for a new school building. He measures the project's performance and progress by looking at the planned value, earned value, and actual cost. Which method is Tucker using to determine the project performance
discretionary dependency
forecasting.
fast tracking
1500
to-complete performance index
1250
earned value management
schedule performance index
Hollie is managing a bathroom renovation project that has a budget of $1,500 and is 40% complete. She planned to spend $500 a month on the three-month project. Hollie is evaluating the status of the project at the end of the first month. What is the
discretionary dependency
forecasting.
fast tracking
1500
to-complete performance index
1250
earned value management
schedule performance index
The project manager would like to show the rate at which the project is progressing compared to what was planned. What indicator should she reference?
discretionary dependency
forecasting.
fast tracking
1500
to-complete performance index
1250
earned value management
schedule performance index
Tucker is the construction project manager for a new school building. With six months left on the project, he is able to determine whether the project is on target by using:
discretionary dependency
forecasting.
fast tracking
1500
to-complete performance index
1250
earned value management
schedule performance index
Ed is adding a home theater room to his home. The project should take five days and cost $2,500 to complete. At the end of the second day, the project is 50% complete. What is the project's earned value at the end of the second day?
discretionary dependency
forecasting.
fast tracking
1500
to-complete performance index
1250
earned value management
schedule performance index
Check it!