1) Alex prefers to complete the plumbing work in his construction projects before completing electrical work. This is an example of a/an:
A
external dependency.
B
abstract dependency.
C
mandatory dependency.
D
discretionary dependency
2) In order to complete the finished attic remodel project on time, Brian decides to hang the ceiling fan while Petrina paints the walls. This is an example of schedule:
A
leading
B
fast tracking
C
crashing
D
shortening
3) Ed is adding a home theater room to his home. The project should take five days and cost $2,500 to complete. At the end of the second day, the project is 50% complete. What is the project's earned value at the end of the second day?
A
500
B
1000
C
750
D
1250
4) The project manager would like to determine the aggregate estimated costs from the individual work packages to create a detailed breakdown of projected costs. In which process is the project manager most likely participating?
A
determine budget
B
estimate costs
C
earned value management
D
control costs
5) Which metric should Carol use to determine her project's future cost efficiency?
A
cost performance index
B
schedule variance index
C
to-complete performance index
D
schedule performance index
6) The project manager would like to show the rate at which the project is progressing compared to what was planned. What indicator should she reference?
A
schedule variance
B
Gantt chart
C
schedule performance index
D
variance report
7) Tucker is the construction project manager for a new school building. With six months left on the project, he is able to determine whether the project is on target by using:
A
performance review(s).
B
the earned value management.
C
forecasting.
D
the cost management plan.
8) A project manager has a number of experts approximating the expense of completing the project's activities. This process is known as:
A
analogous estimating.
B
estimating costs.
C
determining the budget.
D
controlling costs
9) Emily is adding a garden to her yard. She estimates the work to build a raised garden will be $250 per day and will take six days to complete. What is the project's budget at completion?
A
750
B
500
C
1500
D
1000
10) Tucker is the construction project manager for a new school building. He measures the project's performance and progress by looking at the planned value, earned value, and actual cost. Which method is Tucker using to determine the project performance
A
cost management plan
B
performance review(s)
C
forecasting
D
earned value management
11) Hollie is managing a bathroom renovation project that has a budget of $1,500 and is 40% complete. She planned to spend $500 a month on the three-month project. Hollie is evaluating the status of the project at the end of the first month. What is the
A
500
B
1000
C
1500
D
750
*select an answer for all questions
Check Results & Get Answers
Play Games with the Questions Above
Teachers: Create FREE classroom games with your questions
Click for more info!
©2007-2024
ReviewGameZone.com
|
About
|
Privacy
|
Contact
|
Terms
|
Site Map
WAIT! Find what you needed?
×
Still Looking for the Answers?
Have Another Question?
Play a Review Game with These Questions?
Want to Make Your Own Test Like This One?