Adam's Construction has accepted a contract to build a six-story office building. The company is using a timeline from a two-story building project the company completed in the previous month to develop the schedule for this project. Adam's Construct
critical chain method
parametric estimating.
analogous estimating
5.67 months
discretionary dependency.
the earliest a new HVAC system can be ordered from a manufacturer without delaying the project
mandatory dependency.
bottom-up estimating.
The project manager is creating an estimate to set up an office building's electrical system. He has twenty-two years of experience managing similar projects. The client needs the estimate quickly. Which type of estimate is he most likely to provide?
critical chain method
parametric estimating.
analogous estimating
5.67 months
discretionary dependency.
the earliest a new HVAC system can be ordered from a manufacturer without delaying the project
mandatory dependency.
bottom-up estimating.
Gwen is leading a Web design project and has determined that the optimistic time for completion is 2 months, the pessimistic time is 12 months, and the likely time for completion is 5 months. Using three-point analysis (TE = (O + 4L + P) รท 6), what i
critical chain method
parametric estimating.
analogous estimating
5.67 months
discretionary dependency.
the earliest a new HVAC system can be ordered from a manufacturer without delaying the project
mandatory dependency.
bottom-up estimating.
Chandler is setting up a time schedule for beta testing a new software project. Currently, the company has one computer lab compatible with his new program, and there are three other software programs being tested on that lab's systems. Chandler modi
critical chain method
parametric estimating.
analogous estimating
5.67 months
discretionary dependency.
the earliest a new HVAC system can be ordered from a manufacturer without delaying the project
mandatory dependency.
bottom-up estimating.
Which best describes the critical path slack?
critical chain method
parametric estimating.
analogous estimating
5.67 months
discretionary dependency.
the earliest a new HVAC system can be ordered from a manufacturer without delaying the project
mandatory dependency.
bottom-up estimating.
Dennis is unable to estimate the duration of his project with certainty, so he decides to break down the work into activities. He then adds up the total quantity for each of the activity durations. Dennis is using:
critical chain method
parametric estimating.
analogous estimating
5.67 months
discretionary dependency.
the earliest a new HVAC system can be ordered from a manufacturer without delaying the project
mandatory dependency.
bottom-up estimating.
Craig needs to weld the car chassis together before Jim can install the engine. This represents a/an:
critical chain method
parametric estimating.
analogous estimating
5.67 months
discretionary dependency.
the earliest a new HVAC system can be ordered from a manufacturer without delaying the project
mandatory dependency.
bottom-up estimating.
Andy prefers to set up furniture before hanging window treatments for his interior design projects. This is an example of a/an:
critical chain method
parametric estimating.
analogous estimating
5.67 months
discretionary dependency.
the earliest a new HVAC system can be ordered from a manufacturer without delaying the project
mandatory dependency.
bottom-up estimating.