Review Game Zone
Flash Cards
(current)
Games
Teachers
Search
Project Management 4.0 - 5.0 (part A)
Test Description: Project Management 4.0 - 5.0
Instructions: Answer all questions to get your test result.
1) Adam's Construction has accepted a contract to build a six-story office building. The company is using a timeline from a two-story building project the company completed in the previous month to develop the schedule for this project. Adam's Construct
A
parametric estimating.
B
analogous estimating.
C
reserve analysis.
D
three-point estimating.
2) Which best describes the critical path slack?
A
the earliest a new HVAC system can be ordered from a manufacturer
B
the activities on the critical path
C
the earliest a new HVAC system can be ordered from a manufacturer without delaying the project
D
the delay after the drywall is completed in a house to allow it to dry
3) The project manager is creating an estimate to set up an office building's electrical system. He has twenty-two years of experience managing similar projects. The client needs the estimate quickly. Which type of estimate is he most likely to provide?
A
reserve analysis
B
parametric estimating
C
analogous estimating
D
three-point estimating
4) Chandler is setting up a time schedule for beta testing a new software project. Currently, the company has one computer lab compatible with his new program, and there are three other software programs being tested on that lab's systems. Chandler modi
A
reserve analysis
B
critical chain method
C
critical path method
D
schedule compression
5) Maria determines the project duration by overestimating what she calculates by 15%. Maria is using:
A
parametric estimating.
B
reserve analysis estimating.
C
three-point estimating.
D
analogous estimating.
6) Ashlyn's pottery project for art class must dry before she can put on a final coat of glaze. This is an example of a/an:
A
mandatory dependency.
B
external dependency.
C
discretionary dependency.
D
abstract dependency.
7) Craig would like to view a graphical representation of his project's work packages in a timeline bar chart format. Craig should create a:
A
project schedule diagram.
B
milestone chart.
C
schedule compression.
D
Gantt chart.
8) The project manager recognizes his team may fail to meet a deadline, so he assigns the team to do two activities in parallel. This is an example of schedule:
A
fast tracking.
B
crashing.
C
leading.
D
shortening.
9) Which process puts more resources on the critical path?
A
leading
B
crashing
C
fast tracking
D
shortening
10) Gwen is leading a Web design project and has determined that the optimistic time for completion is 2 months, the pessimistic time is 12 months, and the likely time for completion is 5 months. Using three-point analysis (TE = (O + 4L + P) รท 6), what i
A
2.79 months
B
5.67 months
C
3.29 months
D
5 months
11) Dennis is unable to estimate the duration of his project with certainty, so he decides to break down the work into activities. He then adds up the total quantity for each of the activity durations. Dennis is using:
A
reserve analysis.
B
three-point estimating.
C
bottom-up estimating.
D
analogous estimating
12) Eva has been hired to landscape the new community park. She has sixteen weeks to complete the project, which will take a total of twelve weeks. Eva decides to begin the project immediately so that she has extra time for weather delays. Eva is using:
A
three-point estimating.
B
reserve analysis.
C
parametric estimating.
D
analogous estimating
13) Andy prefers to set up furniture before hanging window treatments for his interior design projects. This is an example of a/an:
A
mandatory dependency.
B
discretionary dependency.
C
abstract dependency
D
external dependency.
14) Alex orders all of the plumbing supplies for his construction projects from the same vendor. Due to a recent fire, the vendor is unable to deliver the supplies when needed. This is an example of a/an:
A
external dependency.
B
discretionary dependency.
C
mandatory dependency.
D
abstract dependency.
15) Craig needs to weld the car chassis together before Jim can install the engine. This represents a/an:
A
abstract dependency.
B
external dependency.
C
discretionary dependency.
D
mandatory dependency.
*select an answer for all questions
Check Results & Get Answers
Play Games with the Questions Above
Teachers: Create FREE classroom games with your questions
Click for more info!
©2007-2024
ReviewGameZone.com
|
About
|
Privacy
|
Contact
|
Terms
|
Site Map
WAIT! Find what you needed?
×
Still Looking for the Answers?
Have Another Question?
Play a Review Game with These Questions?
Want to Make Your Own Test Like This One?