Review Game Zone
Flash Cards
(current)
Games
Teachers
Search
Introduction To Information Technology Lesson 10 Review
Test Description: Review of CIW Lesson 10 quiz questions
Instructions: Answer all questions to get your test result.
1) Which result reflects an IT project that is poorly managed?
A
Fewer alternatives are provided to employees
B
Other departments begin to work together more amicably
C
IT training and support is discontinued
D
Tasks take longer to complete and cost more money
2) A SWOT analysis is an integral part of the planning phase because it allows you to:
A
evaluate your organization's or team's strengths
B
outline the requirements for each project task
C
outline the processes, tools and techniques
D
list planned dates for performing tasks meeting goals
3) If the budget for a project were cut in half, which would be the most likely result?
A
No other part of the project would have to be adjusted
B
The time allotted for the project would be cut in half
C
The scope of the project would be reduced
D
The scope of the project would be increased
4) Which statement best describes the difference between intranets and extranets?
A
Intranets are used by Internet industry professionals
B
Intranets are used within a geographic continent
C
Intranets are used by commercial organizations
D
Intranets are used within corporations by employees
5) How does scope creep undermine the success of a project?
A
it occurs in small increments can add up to failure
B
indicates a change in project management expertise
C
it is abrupt significant causing projects to end
D
indicates the project costs are spiraling out of control
6) Which is an interactive Web-based seminar typically conducted from speaker to participants?
A
Webinar
B
Webcast
C
Voice conference
D
Web conference
7) What are the three elements of the project triangle?
A
Time, money and scope
B
Deadlines, time and tasks
C
Funding, quality and deadlines
D
Time, staff and funding
8) Which is the best way to coordinate an interactive meeting for people from different cities?
A
Web conference
B
Podcast
C
Conference call
D
Webcast
9) A needs analysis:
A
identifies problems or desires project must resolve/address
B
identifies the planned dates for performing tasks
C
identifies the requirements for each project task
D
identifies the goals and tasks of a project
10) What can you do during execute control phases to discuss progress respond to project issues
A
Keep an issues log to review at each project milestone
B
Adjust the project schedule accordingly
C
Document project tasks to provide a paper trail
D
Plan and schedule meetings with team members
11) What does a Statement of Work outline?
A
The project tasks and durations in bar-chart format
B
The processes, tools and techniques you will need
C
The planned dates for performing tasks and meeting goals
D
The requirements for each project task
12) In project management, a task is:
A
work units that must be accomplished within a timeframe
B
appointment of a person, dept. or device to a unit of work
C
a person, dept. or device needed to finish a unit of work
D
a unit of work that must be accomplished
13) Which is a Web-based seminar that is interactive between participants and presenter?
A
Webinar
B
Webcast
C
Voice conference
D
Web conference
14) Which of the following is an advantage of using a Webcast instead of an in-person meeting?
A
can be viewed by unauthorized participants
B
might be interrupted by Internet connection problems
C
more cost-effective
D
lacks face-to-face interaction
15) In project management, a project is:
A
person, dept. or device needed to accomplish a unit of work
B
sequence of work units accomplished in a defined time frame
C
appointment of a person, dept. or device to a unit of work
D
unit of work that must be accomplished
16) What are project stakeholders?
A
People or groups that can exert influence over the project
B
Critical paths that describe tasks that must be completed
C
Reporting tools used by project managers
D
Milestones used to measure the progress of a project
17) In contrast to meetings that take place in person, a Webcast offers the advantage of:
A
being available for retransmission any time
B
encouraging participant interactivity
C
broadcasting events in their entirety without interruption
D
enabling participants to communicate with the presenter
18) Milestones can add significant value to project scheduling because:
A
help you manage the changes to the project's scope
B
enable you to determine project team's strong weak points
C
graphically display the project tasks and task durations
D
point where the team stakeholders evaluate progress
19) In project management,an assignment is:
A
a person, dept. or device needed to complete a unit of work
B
sequence of work units that must be done at a certain date
C
a unit of work that must be accomplished
D
appointment of a person, dept. or device to a unit of work
20) During the closing phase a formal project review is done. It provides an opportunity to:
A
test the product, evaluate performances document lessons
B
use the issues log to support time, resource or cost change
C
create a paper trail of team members who performed tasks
D
anticipate and respond to potential project deviations
*select an answer for all questions
Check Results & Get Answers
Play Games with the Questions Above
Teachers: Create FREE classroom games with your questions
Click for more info!
©2007-2024
ReviewGameZone.com
|
About
|
Privacy
|
Contact
|
Terms
|
Site Map
WAIT! Find what you needed?
×
Still Looking for the Answers?
Have Another Question?
Play a Review Game with These Questions?
Want to Make Your Own Test Like This One?