Project Management 3.0 Part B
Test Description: Project Management 3.0 part B
Instructions: Answer all questions to get your test result.
1) Felicia is an event project manager. She is meeting with her conference stakeholders to ensure the scope of products delivered aligns with what was planned for in the scope baseline of the project. Which process is Felicia conducting?
A
define scope
B
verify scope
C
collect requirements
D
control scope
2) Hollie is a financial project manager. Tina asks Hollie's team to produce a financial report at the end of the year that includes her company's income statement and balance sheet. When Hollie's team completes the work and the deliverables are present
A
verifying the scope
B
defining the scope
C
collecting requirements
D
controlling the scope
3) During what process is work decomposition performed?
A
creating WBS
B
defining scope
C
collecting requirements
D
verifying scope
4) Del is a catering project manager in charge of a charity event. He taste tests the cupcakes made by Angela, a member of his catering team. Del determines that Angela over blended the cupcakes because the tops have risen. He asks Angela to fix the cup
A
inspection
B
decomposition
C
estimating
D
variance analysis
5) Steve is in charge of building a house, and he is currently working on the project scope statement. Steve has collected all necessary requirements from the stakeholders. He has determined that he needs to provide three bedrooms, two bathrooms, and a
A
project constraints
B
project acceptance criteria
C
project exclusions
D
project deliverables
6) Once Jim has established a project scope baseline, he can use it to inform the development of the:
A
requirements, scope statement, and WBS dictionary.
B
requirements, scope statement, and WBS.
C
WBS and WBS dictionary.
D
scope statement, WBS, and WBS dictionary.
7) Kristi is in charge of a fundraiser for the nurses' committee. Kristi has completed the project scope statement and requirements documentation. She is currently working on creating a graphic by breaking down all the work that needs to occur to create
A
work breakdown structure dictionary.
B
project scope statement.
C
requirements documentation.
D
work breakdown structure.
8) Albert's team is planning an annual conference. His team has broken the conference down to registration, food, guest speakers, and venue location. Next, his team is going to create tasks for each member of the group. Albert is currently working on th
A
work breakdown structure dictionary.
B
work breakdown structure.
C
requirements documentation.
D
project scope statement.
9) Sarah is in charge of a charity event, and she is currently communicating with the catering company and requesting work performance information regarding their progress to compare to her scope baseline. Sarah is working on which process?
A
control scope
B
define scope
C
verify scope
D
collect requirements
10) Mark meets with the conference project stakeholders to determine and document that the number of rooms and meals needed for the conference aligns with the conference project objectives. Which process is Mark conducting?
A
control scope
B
define scope
C
verify scope
D
collect requirements
11) Which tool or technique will the project manager use in the process of creating a WBS?
A
decomposition
B
inspection
C
variance analysis
D
estimating
12) Dave's team is breaking down a computer science project into work packages so they can determine milestones. Which process is Dave's team participating in?
A
defining scope
B
collecting requirements
C
creating the WBS
D
verifying scope
*select an answer for all questions
Check Results & Get Answers
Play Games with the Questions Above
Teachers: Create FREE classroom games with your questions
Click for more info!
©2007-2024
ReviewGameZone.com
|
About
|
Privacy
|
Contact
|
Terms
|
Site Map
WAIT! Find what you needed?
×
Still Looking for the Answers?
Have Another Question?
Play a Review Game with These Questions?
Want to Make Your Own Test Like This One?