1) Which tool or technique would be useful when developing the project charter?
A
planning guide
B
consumer survey
C
PERT method
D
expert judgement
2) Brian would like to purchase his first home. He is unsure of the inputs needed to help him manage the details of this project. He sets up an appointment with his Uncle Joe, who has owned many real estate properties and is very familiar with the proce
A
consumer survey
B
expert judgment
C
planning guide
D
analytical techniques
3) An employee has been asked to evaluate a project that is experiencing some performance challenges. She asked the project manager to call a meeting with the project sponsor. The project manager replies that he does not know who the project sponsor is.
A
business case
B
project charter
C
project baseline document
D
project plan
4) Angela is a project manager leading a curriculum project. She is working with her team to create an interior design curriculum project for students in her state. Which project management process is Angela performing?
A
execution
B
closing
C
initiation
D
planning
5) The magazine will feature 10 items and will be completed over six months. The cover will be printed in color. The bound pages will be printed in black and white. This description belongs in the graphic design project:
A
business case.
B
statement of work
C
milestones summary.
D
expert judgment
6) Angela is a project manager who leads a curriculum project. She is creating an outline of what each team member needs to complete by when to ensure the deliverable is on time, under budget, and within the scope of the project. Which project managemen
A
execution
B
initiation
C
closing
D
planning
7) Carol develops a detailed description of the project objectives, assumptions, deliverables, and cost for her construction project charter. The narrative description of the project deliverables that she is developing is a/an:
A
change control board.
B
statement of work.
C
expert judgment.
D
stakeholder registry.
8) Anu is a project manager for a construction company building a new home for Mia. After two weeks of the project, Mia comes to Anu and asks for an additional bedroom to be added to the home project. Anu tells Mia that they will need to meet to discuss
A
gifting
B
change control.
C
scope creep
D
gold plating
9) George has described a project to rebuild an antique car. He has defined how much of his personal money he has saved to spend on this project. Kelly will be leading a team that will be executing the deliverables for the project. Who can approve the p
A
project team
B
project manager
C
project stakeholders
D
project sponsor
10) Eugene holds a meeting with his project team to discuss and document what succeeded and failed in their recent project. What process is Eugene facilitating?
A
historical information
B
project termination
C
project close
D
lessons learned
11) Lauren is a project manager who is determining the need for a curriculum project. She is researching the job market to make a business case for the project. Which project management process is Lauren performing?
A
initiation
B
executing
C
closing
D
planning
12) After discovering that some project work failed to be performed according to plan, a project manager analyzes the situation. She then presents what needs to occur to correct the problems to Austin. Austin requests a change in the project to reduce th
A
lessons learned
B
preventive action
C
defect repair
D
corrective action
13) Delores has just been assigned to be a project manager of a team, and she would like to find out more about a project. She is unsure of who can authorize the project. What document should Delores consult?
A
contact
B
project charter
C
project objectives
D
organizational process assets
14) Alan has just been assigned as the project manager for a software development project his company has been awarded. He has been asked to create the project charter and send it to the project sponsor for approval. The main input he needs to develop th
A
He should contact the project sponsor or the customer for the statement of work.
B
He should look in the organizational assets to find the statement of work.
C
He should look in the environmental factors for the statement of work.
D
He should create the project statement of work as the project manager.
15) Cheryl is a project manager leading a conference project. She prepares a document that describes the products and services to be delivered by her team to the stakeholders. She will use this document during the initiation phase to highlight the confer
A
project management plan
B
business case
C
enterprise environment factors
D
project statement of work
16) A project manager is implementing a variety of approved changes to a project. Which would least likely be a type of approved change?
A
preventive action
B
lessons learned
C
corrective action
D
defect repair
*select an answer for all questions
Check Results & Get Answers
Play Games with the Questions Above
Teachers: Create FREE classroom games with your questions
Click for more info!
©2007-2024
ReviewGameZone.com
|
About
|
Privacy
|
Contact
|
Terms
|
Site Map
WAIT! Find what you needed?
×
Still Looking for the Answers?
Have Another Question?
Play a Review Game with These Questions?
Want to Make Your Own Test Like This One?